Project Management
You are the project manager on a project to construct a flyover in
the city to ease traffic congestion. Flyover construction should cause minimum
disruption to the traffic until it is complete. Ensuring safety of the
commuters and workers at the site is the responsibility of your company. The
date of completion of the project is six months from now. This date cannot be
extended because of an upcoming international summit in the city.
To achieve theoverall project time lines, the following
milestones must be achieved:
·
Identifying a temporary alternate route and making
it ready for the commuters—within two weeks of the project start
·
Getting a final approval for the design
and layout of the flyover, including a structural analysis—within four weeks of
the project start
·
Completing all construction activities by the end
of the fifth month
·
Cleaning up the construction infrastructure and
finishing and painting the flyover by the end of five months and two weeks
·
Opening the flyover for a trial in the third week
of the sixth month and gathering feedback
·
Placing traffic signs—entry and exit—in the fourth
week of the sixth month
·
You have to acquire resources
for the project. What type of resources will you require to successfully
execute the project?
Out of the factors
that influence decisions on acquiring human resources, which factors do you
consider to be the most decisive in the choice of human resources for this
project?